| Project | Status | County | Total Acres |
|---|---|---|---|
|
Pond 3
|
Construction completed | Alameda | 110.2 |
|
Pond A4
|
Construction planned | Santa Clara | 306.4 |
|
Port Sonoma Marina Perimeter
|
Construction completed | Sonoma | 8.9 |
|
Ravenswood Triangle
|
Construction completed | San Mateo | 3.0 |
|
Redwood-San Andreas High School Marsh
|
Construction completed | Marin | 15.0 |
|
Pier 98
|
Construction completed | San Francisco | 8.8 |
|
Richardson Bay Bridge Marshes
|
Construction completed | Marin | 6.6 |
|
Richmond Parkway
|
Construction completed | Contra Costa | 3.3 |
|
Ringstorm Bay Unit Marsh Restoration
|
Construction in-progress | Napa | 50.0 |
|
Viansa Winery
|
Construction completed | Sonoma | 94.3 |
|
Nordstrom/Shorebird Marsh
|
Construction completed | Marin | 48.2 |
|
Novato Sanitary District Reclamation Project
|
Construction completed | Marin | 65.0 |
|
River Park
|
Construction planned | Solano | 38.8 |
|
San Leandro Shoreline Marshlands Enhancement Project
|
Construction completed | Alameda | 171.9 |
|
Plummer Creek Wetlands Restoration Mitigation Project
|
Construction completed | Alameda | 26.0 |
|
Rush Creek/Cemetery Marsh Enhancement Project
|
Construction completed | Marin | 272.1 |
|
Sanchez Creek Marsh
|
Construction completed | San Mateo | 3.1 |
|
Burlingame Lagoon
|
Construction completed | San Mateo | 0.3 |
|
Pond A18
|
Construction planned | Santa Clara | 855.6 |
|
San Carlos Airport North Clear Zone
|
Construction completed | San Mateo | 0.6 |
|
Slaughterhouse Point
|
Construction completed | Solano | 275.5 |
|
Bahia Lagoon
|
Construction completed | Marin | 30.1 |
|
Scottsdale Marsh Enhancement Project
|
Construction completed | Marin | 46.4 |
|
Schellville
|
Construction planned | Sonoma | 386.7 |
|
East Shore Park - Schoolhouse Creek
|
Construction planned | Alameda | 2.3 |
|
Seabreeze Marina
|
Construction in-progress | Alameda | 0.3 |
|
Seal Slough
|
Construction completed | San Mateo | 47.2 |
|
Skaggs Island
|
Construction planned | Sonoma | 4,166.8 |
|
Simmons Slough Wildlife Corridor
|
Construction planned | Marin | 186.2 |
|
South Basin Wetlands
|
Construction completed | Alameda | 3.7 |
|
Mare Island Navy Mitigation Marsh
|
Construction planned | Solano | 62.7 |
|
Marta's Marsh
|
Construction completed | Marin | 20.7 |
|
Breuners Mitigation Bank
|
Construction planned | Contra Costa | 109.1 |
|
Color Spot
|
Construction completed | Contra Costa | 1.5 |
|
San Mateo's Master Shoreline Parks Masterplan
|
Construction in-progress | San Mateo | 13.1 |
|
Sonoma Baylands Salt Marsh Restoration
|
Construction completed | Sonoma | 350.0 |
|
South Bay Salt Pond Restoration Project
|
Construction in-progress | Alameda, San Mateo, Santa Clara | 13,502.7 |
|
Western Stege Marsh Restoration
|
Construction in-progress | Contra Costa | 9.4 |
|
Tasman Corridor Light Rail Transit Mitigation Project
|
Construction in-progress | Santa Clara | 3.6 |
|
Marin Flood Control - Seasonal
|
Construction completed | Marin | 343.4 |
|
Edgerley Island Marina
|
Construction completed | Napa | 9.4 |
|
Figueras Tract
|
Construction planned | Solano | 72.7 |
|
Triangle Marsh, Refuge Entry
|
Construction in-progress | Alameda | 9.4 |
|
Tolay Creek
|
Construction completed | Sonoma | 305.5 |
|
Treasure Island
|
Construction planned | San Francisco | 16.7 |
|
Triangle Marsh at Hayward Shoreline
|
Construction completed | Alameda | 8.7 |
|
Stevens Creek Tidal Marsh
|
Construction completed | Santa Clara | 30.6 |
|
Triangle Marsh Restoration Project
|
Construction completed | Marin | 15.9 |
|
East Shore Park - Strawberry Creek
|
Construction planned | Alameda | 1.7 |
|
Nevada Parcel
|
Construction completed | Contra Costa | 109.0 |
|
Sunnyvale Baylands Park
|
Construction completed | Santa Clara | 12.4 |
|
Tubbs Island Marsh Restoration Project
|
Construction completed | Sonoma | 68.4 |
|
Vallejo Mitigation Sites
|
Construction completed | Solano | 137.4 |
|
Bayside Business Park - Phase II
|
Construction completed | Alameda | 88.0 |
|
Bayside Business Park - Phase I
|
Construction completed | Alameda | 271.0 |
|
Whipple Ave Mitigation
|
Construction completed | San Mateo | 7.7 |
|
Warm Springs Pasture
|
Construction planned | Alameda | 276.0 |
|
West End Duck Club
|
Construction completed | Napa, Solano | 355.2 |
|
White Slough
|
Construction completed | Solano | 94.1 |
|
Whales Tail
|
Construction completed | Alameda | 254.0 |
|
Zanker Road Landfill Mitigation Site
|
Construction completed | Santa Clara | 25.0 |
|
Montezuma Wetlands Project
|
Construction in-progress | Solano | 2,229.0 |
|
Hayward Shoreline Enhancement Project
|
Construction completed | Alameda | 80.3 |
|
Foster City Mitigation Sites
|
Construction in-progress | San Mateo | 29.2 |
|
Hoffman Marsh Wetland Mitigation Project
|
Construction completed | Contra Costa | 6.0 |
|
Las Gallinas Ponds
|
Construction planned | Marin | 68.4 |
|
Huichica Creek Unit
|
Construction in-progress | Sonoma | 51.0 |
|
Harvey Marsh
|
Construction completed | Santa Clara | 52.0 |
|
Ideal Marsh
|
Construction completed | Alameda | 129.4 |
|
Emily Renzel Marsh
|
Construction completed | Santa Clara | 36.0 |
|
KGO Towers
|
Construction completed | Alameda | 1.3 |
|
Lake Merritt Restoration
|
Construction planned | Alameda | 153.3 |
|
La Riviere Marsh
|
Construction completed | Alameda | 117.6 |
|
Madera del Presidio Project - Phase I and II
|
Construction completed | Marin | 100.0 |
|
Mare Island Navy Conservation Areas
|
Construction planned | Solano | 106.3 |
|
Mayhew's Landing
|
Construction planned | Alameda | 110.4 |
|
Mare Island Refuge
|
Construction planned | Solano | 169.9 |
|
Marin Flood Control/CDFG - Perennial
|
Construction completed | Marin | 309.2 |
|
Miller Creek
|
Construction completed | Marin | 12.0 |
|
Mill Valley Marsh
|
Construction completed | Marin | 6.5 |
|
MLK Jr. Regional Shoreline Wetlands Project
|
Construction completed | Alameda | 70.6 |
|
Moseley Tract
|
Construction planned | San Mateo | 61.0 |
|
Mountain View Tidal Marsh
|
Construction completed | Santa Clara | 28.9 |
|
Muzzi Marsh
|
Construction completed | Marin | 147.9 |
|
South Napa Wetland Opportunity Area
|
Construction completed | Napa | 940.1 |
|
Napa Sonoma Marsh Restoration Project
|
Construction in-progress | Napa, Sonoma | 7,322.4 |
|
New Chicago Marsh
|
Construction completed | Santa Clara | 387.0 |
|
North Basin Wetlands
|
Construction completed | Alameda | 5.0 |
|
Novato Creek Antenna Field
|
Construction planned | Marin | 134.2 |
|
North Bothin Marsh Enhancement Project
|
Construction completed | Marin | 0.4 |
|
Galbraith Golf Course Wetland Mitigation Project
|
Construction completed | Alameda | 8.0 |
|
Guadalcanal Village Restoration Project
|
Construction completed | Solano | 55.5 |
|
Oakland Middle Harbor Enhancement Project
|
Construction in-progress | Alameda | 4.9 |
|
Hayward Shoreline Enhancement Project-Oliver Salt Ponds
|
Construction planned | Alameda | 134.0 |
|
Oro Loma Marsh Mitigation Project
|
Construction completed | Alameda | 21.0 |
|
Oro Loma Marsh Enhancement Project
|
Construction in-progress | Alameda | 315.3 |
|
Pacific Commons Development
|
Construction completed | Alameda | 492.0 |
|
Pacheco Pond
|
Construction completed | Marin | 110.9 |
|
Palo Alto Harbor Improvements
|
Construction completed | Santa Clara | 14.3 |
|
Perry Gun Club Mitigation Project
|
Construction in-progress | Alameda | 16.8 |
|
Petaluma River Marsh
|
Construction completed | Sonoma | 45.8 |
|
Petaluma Marsh Expansion Project
|
Construction in-progress | Marin | 108.3 |
|
Pier 94
|
Construction in-progress | San Francisco | 7.7 |
|
Albany Bulb Lagoon
|
Construction planned | Alameda | 6.7 |
|
American Canyon Ecosystem Enhancement Project
|
Construction completed | Napa | 610.0 |
|
Bair Island SFO Mitigation
|
Construction completed | San Mateo | 220.1 |
|
Bair Island Restoration Project
|
Construction in-progress | San Mateo | 1,385.5 |
|
Albany Salt Marsh Expansion
|
Construction planned | Alameda | 3.6 |
| Central Avenue Marsh - Albany Sequel | Construction completed | Alameda, Contra Costa | <0.1 |
|
Pacific Shores Center
|
Construction completed | San Mateo | 146.2 |
|
Northern Outer Bair Island
|
Construction completed | San Mateo | 551.7 |
|
Bel Marin Keys Unit V
|
Construction in-progress | Marin | 1,564.4 |
|
East Shore Park - Berkeley Meadows
|
Construction planned | Alameda | 55.2 |
|
Bothin Marsh
|
Construction completed | Marin | 0.5 |
|
Canalways
|
Construction planned | Marin | 101.8 |
|
Cargill Mitigation Marsh
|
Construction completed | Alameda, San Mateo | 49.2 |
|
Central Avenue Marsh
|
Construction completed | Contra Costa | 2.9 |
| Coyote Creek Lagoon | Construction completed | Alameda | 8.0 |
|
Cerrito Creek at Albany Hills
|
Construction completed | Alameda | 1.1 |
|
Cogswell Marsh
|
Construction completed | Alameda | 229.1 |
|
DUST Marsh
|
Construction completed | Alameda | 15.0 |
|
Charleston Slough Tidal Marsh Restoration Project
|
Construction completed | Santa Clara | 101.3 |
|
Citation Marsh
|
Construction completed | Alameda | 95.4 |
|
Colma Creek Mitigation
|
Construction completed | San Francisco, San Mateo | 1.6 |
|
Cooley Landing
|
Construction completed | San Mateo | 118.4 |
|
Corte Madera Ecological Reserve Expansion
|
Construction completed | Marin | 8.3 |
|
Crissy Field
|
Construction completed | San Francisco | 13.5 |
|
Cullinan Ranch
|
Construction planned | Solano, Napa | 1,564.1 |
|
Hayward Marsh Brackish
|
Construction completed | Alameda | 60.0 |
|
Coyote Creek Flood Control Project
|
Construction completed | Santa Clara | 66.6 |
|
Damon Slough Seasonal Wetland Mitigation
|
Construction completed | Alameda | 9.8 |
|
Deak Marsh
|
Construction completed | Marin | 0.6 |
|
Dunphy Park
|
Construction completed | Marin | 0.8 |
|
Hayward Marsh Fresh
|
Construction completed | Alameda | 85.9 |
|
Eden Ecological Preserve Restoration Project
|
Construction completed | Alameda | 767.6 |
|
East San Rafael Wetlands
|
Construction completed | Marin | 13.0 |
|
Faber Tract Marsh
|
Construction completed | San Mateo | 87.3 |
|
Gallinas Creek Restoration Project - Phase1, 2, and 3
|
Construction completed | Marin | 19.5 |
|
Emeryville Crescent
|
Construction completed | Alameda | 50.3 |
|
Green Point/Toy Marsh
|
Construction completed | Marin | 57.4 |
|
Hamilton Wetlands Restoration Project
|
Construction in-progress | Marin | 1,451.2 |
|
Belden's Landing
|
Construction completed | Solano | 15.2 |
|
Bayside Business Park - December 2002
|
Construction in-progress | Alameda | 17.0 |
|
Eden Ecological Preserve Restoration Project - Dixon Landing Road Project
|
Construction in-progress | Alameda, Santa Clara | 17.5 |
|
Leonard Ranch Wetlands Restoration Project
|
Construction completed | Sonoma | 334.8 |
|
Novato Creek Flood Control Project
|
Construction completed | Marin | 8.0 |
|
Lakeside Drive & Mariner's Island Extension Mitigation
|
Construction completed | San Mateo | 1.9 |
|
Triangle Marsh at Larkspur
|
Construction in-progress | Marin | 1.0 |
|
Camp 2 Wingo Unit Marsh Restoration
|
Construction in-progress | Napa, Sonoma | 608.0 |
|
Gianulius Property
|
Construction completed | Solano | 2.1 |
|
I-80 Improvements/HOV Land Project
|
Construction completed | Alameda | 2.8 |
|
Shell Marsh Restoration Project at Peyton Slough
|
Construction in-progress | Contra Costa | 200.0 |
|
Island Slough Wetland Development Project
|
Construction completed | Solano | 354.0 |
|
West Navy Marsh
|
Construction completed | Contra Costa | 64.4 |
|
Hill Slough West Restoration Project
|
Construction planned | Solano | 223.0 |
|
Martinez Regional Shoreline Salt Marsh Enhancement Project
|
Construction completed | Contra Costa | 11.0 |
|
Blacklock Tidal Marsh Restoration
|
Construction completed | Solano | 70.0 |
| Carquinez Bridge Seismic Retrofit Project | Construction in-progress | Solano | 0.7 |
|
Brisbane Baylands
|
Construction in-progress | San Francisco, San Mateo | 32.0 |
|
Route 101/Ralston Ave. Interchange
|
Construction in-progress | San Mateo | 1.9 |
|
Wildcat Creek Marsh Restoration Project
|
Construction completed | Contra Costa | 279.7 |
|
Point Buckler
|
Construction completed | Solano | 49.5 |
|
Ryer Island
|
Construction completed | Solano | 929.2 |
|
Wheeler Island
|
Construction completed | Solano | 98.0 |
|
Chipps Island East
|
Construction completed | Solano | 270.0 |
|
Chipps Island West
|
Construction completed | Solano | 148.0 |
|
CalTrans Mitigation Site
|
Construction completed | Solano | 21.6 |
|
U.S. Maritime Administration Marsh
|
Construction completed | Solano | 69.6 |
|
Madera Bay Park
|
Construction completed | Marin | 4.9 |
|
Huichica Creek Enhancement
|
Construction completed | Napa, Sonoma | 105.5 |
|
Castro Cove
|
Construction in-progress | Contra Costa | 20.0 |
|
Codornices Creek Restoration - Nagai Property
|
Construction planned | Alameda | <0.1 |
|
Sky Ranch Stock Pond Rehabilitation
|
Construction planned | Contra Costa | 0.3 |
|
Refugio Creek Bridge Project
|
Construction planned | Contra Costa | 0.4 |
|
Deer Valley Wetland Restoration
|
Construction planned | Santa Clara | 2.7 |
|
Polhemus Creek Restoration Project
|
Construction planned | San Mateo | 0.2 |
|
McGarvey Gulch Salmonid Barrier Improvements Project
|
Construction planned | San Mateo | 0.6 |
|
Downtown Sewer, Water, and Storm Drain Improvements
|
Construction planned | Contra Costa | <0.1 |
|
12th Street Reconstruction Project
|
Construction planned | Alameda | 0.7 |
|
Reconstruction of Bollinger Road Bridge over Calabazas Creek
|
Construction planned | Santa Clara | 0.5 |
|
Barron Creek at 1018 Los Robles Avenue
|
Construction planned | Santa Clara | <0.1 |
|
Webb Ranch Mitigation Site
|
Construction planned | San Mateo | 2.7 |
| Bailey Estates | Construction planned | Contra Costa | 5.7 |
|
Zone 12 Lines H, J, and K Sediment Removal Project
|
Construction planned | Alameda | 3.2 |
|
Fairfield Corporate Commons Project
|
Construction planned | Solano | 2.3 |
|
Lower Walnut Creek Emergency Interim Protection
|
Construction planned | Contra Costa | 8.2 |
|
Inverness Ridge
|
Construction planned | Alameda | 0.7 |
|
Elsie Gridley Mitigation Bank
|
Construction in-progress | Solano | 441.2 |
|
Adobe Creek Upper Reach 5 Restoration Project
|
Construction planned | Santa Clara | 0.8 |
|
Dan Wilson Creek Bridge Project
|
Construction planned | Solano | 1.1 |
|
Elsie Roemer Enhancement Project
|
Construction planned | Alameda | 0.6 |
|
Kingdom Hall of Jehovah's Witnesses
|
Construction planned | Napa | 0.2 |
|
Castro Valley Creek Daylighting Project
|
Construction planned | Alameda | 0.8 |
|
American Canyon Creek Restoration
|
Construction planned | Napa | 1.1 |
| Can Duck Club | Construction planned | Napa | <0.1 |
|
Carriger Creek Enhancement
|
Construction planned | Sonoma | 1.0 |
|
City of Calistoga Bank Stabilization
|
Construction planned | Napa | 0.1 |
|
Gasser, Vernice/FHK Investment - Gasser Estate Wetland Mitigation
|
Construction planned | Napa | 1.0 |
|
Ghisletta Project Site
|
Construction planned | Napa | 1.6 |
|
John F. Kennedy Park Wetland Enhancement Project
|
Construction planned | Napa | 17.0 |
|
Kennedy Park Master Plan
|
Construction planned | Napa | <0.1 |
|
Napa Air Center Wetland Preserve
|
Construction planned | Napa | 0.6 |
|
Napa Meadows Development
|
Construction planned | Napa | 9.9 |
|
Napa River Bank Stabilization - Carpy-Connolly Ranch
|
Construction completed | Napa | 0.7 |
|
Napa River Oxbow Preserve
|
Construction in-progress | Napa | 37.3 |
|
Napa River, Gasser Wetland Relocation
|
Construction planned | Napa | 9.5 |
| Napa Urban Waterfront Restoration | Construction completed | Napa | <0.1 |
|
Napa Valley Gateway Business Park and Sheehy Creek Realignment and Enhancement Project
|
Construction completed | Napa | 5.4 |
|
Napa Valley Unified School District Site
|
Construction in-progress | Napa | 314.1 |
| Palmaz Vineyards Creek Restoration | Construction planned | Napa | <0.1 |
|
Pioneer Bank Stabilization Project
|
Construction completed | Napa | <0.1 |
|
St. Helena Comprehensive Flood Protection Project
|
Construction in-progress | Napa | 7.8 |
|
Sulphur Creek Restoration Project
|
Construction completed | Napa | 0.8 |
|
First Street Highway 29 Interchange
|
Construction completed | Napa | 0.2 |
|
Upper York Creek Dam Sediment Removal Project
|
Construction planned | Napa | 2.0 |
|
McNabney Marsh/Peyton Slough Dredging and Water Control Structure Project
|
Construction planned | Contra Costa | 137.0 |
|
Loukos Property Stream Bank Repair Project Site
|
Construction planned | Contra Costa | <0.1 |
|
Granada High School Crossing Removal Project
|
Construction planned | Alameda | <0.1 |
|
Southbound Interstate 680 Sunol Grade Modified HOV Lane Widening Project
|
Construction planned | Alameda | 6.3 |
|
Front Street Bank Stabilization Project
|
Construction planned | Contra Costa | <0.1 |
|
Hall Wines - Dry Creek Fish Barrier Removal and Enhancement Project
|
Construction planned | Napa | 2.0 |
|
Roaring River 20-3 Natural Gas Exploration Project
|
Construction planned | Solano | 1.0 |
|
Mills College Lion Creek Stream Channel Stabilization
|
Construction planned | Alameda | 0.5 |
|
Azaya Ranch Vineyard Project - Phase I and II
|
Construction planned | Marin | 3.7 |
|
Preserve at Redwood Shores Mitigation Bank
|
Construction planned | San Mateo | 90.0 |
|
Restoration of Zone 5 Line F-1 Flood Control Channel
|
Construction planned | Alameda | <0.1 |
|
Mare Island Northgate Interchange Project
|
Construction planned | Napa | 7.7 |
|
North Suisun Mitigation Bank/Keswick Village
|
Construction planned | Solano | 5.8 |
|
Zone 2 Line C Flood Control Channel from Line A to East 14th Street
|
Construction planned | Alameda | <0.1 |
|
Zone 6 Line E Bank Failure Repair Upstream of Fremont Boulevard
|
Construction planned | Alameda | <0.1 |
|
California Department of Transportation Caldecott Tunnel Improvement Project
|
Construction planned | Alameda, Contra Costa | <0.1 |
|
California Department of Transportation Conn Creek Slide Repair Project
|
Construction planned | Napa | <0.1 |
|
Union Sanitary District Force Main Access Improvement Project
|
Construction planned | Alameda | 0.2 |
|
San Ramon Creek Realignment at El Capitan Drive Bridge
|
Construction planned | Contra Costa | 0.4 |
|
Zone 4 Line A Improvements Between Cabot Blvd. and UPRR
|
Construction planned | Alameda | 2.4 |
|
Olema RV Resort and Campground Diversion Ditch Restoration Project
|
Construction planned | Marin | 0.4 |
|
Zone 3A Line A Sediment Improvement Project From I-880 to Southern Pacific Railroad
|
Construction planned | Alameda | 15.5 |
|
Rindel Creek Mitigation Project for Reis Avenue
|
Construction planned | Solano | 0.3 |
|
Waterman Water Treatment Plant Expansion Project
|
Construction planned | Solano | 1.9 |
|
Hanna Court Warehouse Project Site
|
Construction planned | Napa | 8.9 |
|
Carlos Place Subdivision
|
Construction planned | Contra Costa | 0.1 |
|
Mission San Jose Water Treatment Plant Access Road Erosion Mitigation Project
|
Construction planned | Alameda | <0.1 |
|
Bernal Avenue Bridge and Road Widening Project
|
Construction planned | Alameda | 3.5 |
|
The Acacia Creek at Union City Development Project
|
Construction planned | Alameda | 1.0 |
|
Arroyo Seco Improvement Program
|
Construction planned | Alameda | 10.6 |
|
Bayfront Park Tidal Wetland Restoration Project
|
Construction planned | Marin | 0.3 |
|
Waldo Point Harbor
|
Construction planned | Marin | 0.9 |
|
Hiddenbrooke - Phase 3
|
Construction planned | Solano | 1.0 |
|
Lenihan Dam Oultet Modification Project
|
Construction planned | Santa Clara | <0.1 |
|
State Route 87 Detour II Sanitary Sewer Reconstruction Project - Phase II
|
Construction planned | Santa Clara | <0.1 |
|
Dutch Slough Tidal Marsh Restoration Project
|
Construction planned | Contra Costa | 1,166.0 |
|
Yosemite Slough Restoration Project
|
Construction planned | San Francisco | 12.0 |
|
Bahia Wetland Restoration
|
Construction planned | Marin | 674.3 |
|
Southhampton Bay Marsh Enhancement & Interpretive Project
|
Construction planned | Solano | 210.0 |
|
Napa Plant Site
|
Construction in-progress | Napa | 1,460.0 |
|
Sears Point Restoration Project
|
Construction planned | Sonoma | 2,327.0 |
| India Basin Wetland Creation and Enhancement Project | Construction planned | San Francisco | <0.1 |
|
Gateway Tech Center Wetland Mitigation Site
|
Construction planned | Alameda | 17.6 |
| Skyway Landing Muted Tidal Marsh Mitigation | Construction planned | San Mateo | 1.1 |
| Suisun City Wetland Mitigation | Construction planned | Solano | 1.4 |
|
Bayfront Park Wetlands Restoration Project
|
Construction planned | Contra Costa | 2.0 |
| East Third Avenue Landfill Closure | Construction planned | San Mateo | 4.9 |
| San Leandro Shoreline Restoration Project | Construction planned | Alameda | 8.5 |
|
El Corte de Madera Creek Watershed Protection Program
|
Construction planned | San Mateo | <0.1 |
|
Ashford Village
|
Construction planned | Solano | 1.7 |
|
Grizzly Island Road Bridge 23C-184 Construction at Hill Slough
|
Construction planned | Solano | 1.3 |
|
Zone 12 Lines I Maintenance Sediment Removal Project, City of Oakland
|
Construction planned | Alameda | 0.2 |
|
Alhambra Highlands Mitigation
|
Construction planned | Contra Costa | 1.7 |
|
Hillview Estates, Subdivision 8533
|
Construction planned | Contra Costa | 1.0 |
|
San Mateo Existing Creek Bank Retaining Wall Repair
|
Construction planned | San Mateo | <0.1 |
|
Maintenance Cleaning of Sediment from Culvert, Old Bear Valley Creek Channel, and Silver Hills Creek Drainage Ditches
|
Construction planned | Marin | <0.1 |
|
John Muir Drive Erosion Control Project
|
Construction planned | San Francisco | <0.1 |
|
Sediment Removal Work at Wildcat Creek from Rumrill Bridge to the Restoration Site
|
Construction planned | Contra Costa | 0.2 |
|
Pavon Creeks and Scow Canyon Restoration Project
|
Construction planned | Contra Costa | 22.0 |
|
Elsie Gridley Mitigation Bank/C-17 Assault Landing Zone
|
Construction planned | Solano | 1.6 |
|
Holdener Park Mitigation Project
|
Construction planned | Alameda | 0.9 |
|
Belmont Creek Maintenance Dredging
|
Construction planned | San Mateo | <0.1 |
|
Sulphur Creek Enhancement Project
|
Construction planned | Alameda | 1.2 |
|
Cedar Street Drainage Project
|
Construction planned | San Mateo | <0.1 |
|
Vineyard Creek Channel Enhancement Project
|
Construction planned | Marin | 1.7 |
|
Alhambra Valley Road Bank Repair
|
Construction planned | Contra Costa | <0.1 |
|
Environmental Volunteers EcoCenter
|
Construction planned | Santa Clara | 0.1 |
|
Old Ranch
|
Construction planned | Contra Costa | 0.5 |
|
EBMUD Moraga Road Pipeline Project
|
Construction planned | Contra Costa | 0.4 |
|
North Suisun Mitigation Bank
|
Construction completed | Solano | 173.6 |
|
Elsie Gridley Mitigation Bank/Mission Solano Rescue Mission
|
Construction planned | Solano | 1.4 |
| Red Top Road Truck Climbing Lane Project | Construction in-progress | Solano | <0.1 |
| Yountville Inn Expansion and Workforce Housing Project | Construction in-progress | Napa | <0.1 |
| Isabel Ave/Interstate 580 Interchange Improvement Project | Construction in-progress | Alameda | <0.1 |
|
Elsie Gridley Mitigation Bank/Fairfield-Suisun Sewer District Waste Water Treatment Plant Improvement Project
|
Construction in-progress | Solano | 4.5 |
|
Steelhead Habitat Enhancement Project (SHEP)
|
Construction planned | San Mateo, Santa Clara | 0.4 |
|
Recovery Action Plan for the San Francisco Garter Snake
|
Construction planned | San Francisco | 0.7 |
|
Kirby Hills Natural Gas Storage Facility - Phase II
|
Construction planned | Solano | 1.0 |
|
Wilder Project
|
Construction planned | Contra Costa | 0.1 |
|
Biagi Distribution Center
|
Construction planned | Napa | 2.4 |
|
20 & 40 Hilton Court Slide Repair
|
Construction planned | Contra Costa | <0.1 |
|
Salvador Channel Bank Restoration & Erosion Control Project
|
Construction planned | Napa | <0.1 |
|
Bay Area Rapid Transit District (BART) Warm Springs Extension
|
Construction planned | Alameda | 17.1 |
|
Storm Damage Repair on Route 1 PM 2.6
|
Construction planned | Marin | <0.1 |
|
Improvements at 353 West Baltimore Avenue in Larkspur
|
Construction planned | Marin | <0.1 |
|
125 Fox Hollow Road Bank Repair - Bear Gulch Creek, Woodside
|
Construction planned | San Mateo | <0.1 |
|
Orinda Oaks Development
|
Construction planned | Contra Costa | 0.2 |
|
Washington Creek Sediment Removal Project
|
Construction planned | Sonoma | 0.2 |
|
Stone Bridge Estates
|
Construction planned | Contra Costa | <0.1 |
|
Jacques Gulch Restoration Project
|
Construction planned | Santa Clara | 3.1 |
|
San Ramon Valley YMCA
|
Construction planned | Contra Costa | 2.2 |
|
Braddock & Logan-Fallon Village
|
Construction planned | Alameda | 8.5 |
|
Vineyard Avenue Project
|
Construction planned | Alameda | <0.1 |
|
Union Sanitary District's Irvington Pump Station Holding Pond
|
Construction planned | Alameda | 1.3 |
|
Elsie Gridley Mitigation Bank/Benicia Bridge Replacement
|
Construction planned | Solano | <0.1 |
|
Elmhurst Creek Sediment Removal and maintenance Project
|
Construction planned | Alameda | 0.4 |
|
Ignacio Creek HOA Culvert Outfall Repairs
|
Construction planned | Marin | 0.1 |
|
Elsie Gridley Mitigation Bank/Meyer Warehouse Project - Phase II
|
Construction planned | Solano | <0.1 |
|
Deepwater Slough Island
|
Construction completed | San Mateo | 5.8 |
|
Interstate 80 High-Occupancy Vehicle Lane Project
|
Construction planned | Solano | 0.2 |
|
Napa Commerce Center
|
Construction planned | Napa | 4.6 |
|
Hopper Creek Diversion Structure Bank Stabilization
|
Construction planned | Napa | <0.1 |